Nathan needs to overlap a task for 25% of its predecessor's duration. Which value must he enter in the link's Lag field to accomplish this

Answer :

Since Nathan needs to overlap a task for 25%, the value that must be entered in the link's Lag field will be -25%.

What is a task?

A task means an activity that needs to be accomplished within a defined period of time.

Lead time is the overlap between tasks that have a dependency. Since he wants to overlap tasks, he would want lead time and lead time is a negative value so he must enter -25% in the lag field.

Learn more about tasks on:

https://brainly.com/question/25748643