Answer :
The quality management concept which must be well-defined at the beginning of the project to help avoid rework and schedule delays is requirements.
Requirements management
- Requirements management and quality management go hand in hand. Clear, well-defined requirements lead to less rework and schedule delays.
In conclusion, we can conclude that the correct answer is requirements management.