1. Green Construction Co. has consistently used the percentage-of-completion method of recognizing revenue. During 2014, Green entered into a fixed-price contract to construct an office building for $24,000,000. Information relating to the contract is as follows:
At December 31
2014 2015
Percentage of completion 15% 45%
Estimated total cost at completion $18,000,000 $19,200,000