Answer :
Answer:
the variable overhead rate variance is $596 favorable
Explanation:
The computation of the variable overhead rate variance is shown below:
= Standard overhead rate × actual direct labor hour - actual overhead
= $7 × 1,490 direct labor hours - $9,834
= $10,430 - $9,834
= $596 favorable
hence, the variable overhead rate variance is $596 favorable