Answer :
Answer:
Results are below.
Explanation:
Giving the following information:
Total estimated overhead costs= (172,550*4)= $690,200
Total estimated units= 23,800
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 690,200 / 23,800
Predetermined manufacturing overhead rate= $29 per unit
Now, we can allocate overhead to each month:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
January= 29*5,300= $153,700
February= 7,300*29= $211,700
March= 29*4,800= $139,200
April= 29*6,400= $185,600
Finally, the unitary total cost:
Unitary cost= 18 + 29= $47