Answer :
Answer:
A. $130,000.
Explanation:
To get the beginning work in progress
= Cost of Manufactured goods + Ending Work - cost of manufacturing during the time period
Manufacturing costs is gotten by;
Dm + DL +MO
DL = direct labor
Dm = direct manufacturing
MO = manufacturing overhead
= 80000 + 140000 + 240000
= $460000
Then we are to get beginning work
= 520000+70000-460000
= $130,000