you are considering two mutually exclusive projects with the following cash flows. which project(s) should you accept if the discount rate is 5 percent? what if the discount rate is 11 percent? year project a project b 0 -$80,000 -$80,000 1 $26,000 $32,000 2 $30,000 $28,000 3 $34,000 $24,000